Review Question Answers
Chapter 1: Introduction to the Building Industry
- Commercial Building, Infrastructure, Industrial, and Residential
- False
- a. Industrial
b. Commercial Building
c. Residential
d. Infrastructure
e. Industrial
f. Residential
g. Infrastructure
h. Commercial Building (Note that even though it will house residents, this is considered a commercial building) - True
- False
- True
Chapter 2: The Lifecycle of a Building Project
- Plan Facility, Design Facility, Construct Facility, and Operate Facility
- False
- True
- True
- Schematic Design (SD), Design Development (DD), Construction Documentation (CD)
Chapter 3: Project Participants and Roles
- False
- True
- False
- True
- True
Chapter 4: Project Delivery Methods
- True (for this class – note that many people use different conventions)
- True
Chapter 5: Introduction to Construction Cost Estimating
- Rough Order of Magnitude; Square Foot; Assemblies; and Detailed
- Land Cost
- True
- 5,497
- False
Chapter 6: Rough Order of Magnitude (ROM) Cost Estimating
- False
- $ 143 / SF
- 15,400 gross square feet (GSF)
Chapter 7: Modeled Square Foot (SF) Cost Estimating
- True
- True
- True
- True
Chapter 8: Assemblies Cost Estimating
- False
- True
Chapter 9: Unit Price Cost Estimating
Chapter 11: General Conditions and Project Staffing
Chapter 12: Introduction to Project Scheduling
Chapter 13: Network Scheduling
Chapter 14: Designing a Site Utilization Plan
Chapter 17: Introduction to Project Management and Control
Chapter 18: Cost and Financial Management
Chapter 19: Schedule Management
Chapter 20: Quality Management
Chapter 22: Managing Information for Projects
Chapter 23: Introduction to Lean Construction
Chapter 25: Managing an Organization